Eti Copper Siirt flotation plant revision studies
,
 
,
 
 
 
More details
Hide details
1
Eti Bakır Co. - General Director
 
2
Eti Bakır Co. - Plant Manager
 
3
Eti Bakır Co. - Process Engineer
 
 
Publication date: 2023-05-21
 
 
Corresponding author
Ahmet Hasyamanlar   

Eti Bakır Co. - Process Engineer
 
 
Physicochem. Probl. Miner. Process. 2023;59(5):166260
 
KEYWORDS
TOPICS
ABSTRACT
Several optimization studies were made to increase metal recovery and reduce operational costs of the concentrator in Siirt Madenköy copper mine. In consequence of these studies, effects of the changes in operating parameters, cost and plant recovery will be examined at this article. In this article, we will discuss two important revision studies, which are: - Replacement of 500 mm hydrocyclone set used in ball mills with 350 mm of hydrocyclone set. - Replacing the present Ball Mill with a SAG mill. Correspondingly elimination of the crushing and screening plant. - Increasing the scavenger cells from 4 to 6 by the addition of 2 more cells. In consequence with this feeding the middling tail to the increased scavenger cells which was treated as a part of final tail before this change. We will examine the effect of all these changes to the final recovery, concentrate grade and final cost.
Special issue paper IMPS2022
eISSN:2084-4735
ISSN:1643-1049
Journals System - logo
Scroll to top